Your Logo

City of Delray Beach Barwick Road Roadway and Pedestrian Improvements Project

City of Delray Beach Barwick Road Roadway and Pedestrian Improvements Project

City Project Number:17-099

ITBC No.: 2024-009

FDOT LAP Project Number:441532-1-58-01

Federal Aid Project ID:D422-086B

FDOT LAP Contract:G2L44

Project Limits: Barwick Road from SR 806/Atlantic Avenue to Lake Ida Road

Virtual Public Meeting:

PDF IconBarwick Presentation

Start Date: June 3, 2024

Completion Date: Summer 2026

Estimated Construction Cost: $7.8 million

Project Funding:  The City of Delray Beach was awarded a federally ­funded grant by the Transportation Planning Agency of Palm Beach County (TPA) under its Local Initiatives Program to improve Barwick Road from West Atlantic Avenue to Lake Ida Road with a focus on pedestrian and bicycle accommodation and complete streets. This is particularly important relative to the Carver Middle School in the northeast quadrant of Barwick Road and Atlantic Avenue.

The current roadway consists of two 11’ travel lanes with a swale on either side. A continuous sidewalk runs along the east side of the road throughout the project limits. The project is a Complete Streets project and is intended to improve environment for all road users, including motorists, cyclists, pedestrians, and individuals with disabilities.

Scope of Work:

Project improvements include milling and resurfacing the existing roadway, drainage improvements, constructing a ten-foot shared-use path on the west side of the roadway and a 6-foot sidewalk on the east side, installation of midblock pedestrian crossing and school zone flashers, street lighting infrastructure, and irrigation.

Project Hotline Number: 561-285-1690

Email: delrayhotline@gmail.com

Documents:

PDF IconBarwick Road Public Meeting Flyer

Project Photos

Barwick Road – January 2025

Drainage Installations

Drainage Installations

Barwick Road – December 2024

Drainage Installations

Drainage Installations

Barwick Road – November 2024

Compaction Operations

Drainage Structure Installation

Barwick Road – October 2024

Drainage Pipe Installations

Roadway Restoration over Drainage Pipe

Barwick Road – September 2024

Drainage Pipe Installation

Backfill Density Testing

Barwick Road – August 2024

Mobilization for Drainage Construction

Silt Fence Installations

Project Map:

Pre-Construction

20230711_152409 20230711_152405 20230711_151656